THE RECONSTRUCTION OF ON-SHORE PUMPING STATION COMBINED WITH A WATER INLET WITHOUT A STOP OF WORK OF CHELYABINSK METALLURGICAL PLANT

Authors

  • Irina Anatolevna Arkanova Author
  • Andrey Andreyevich Noskov Author

Abstract

The plan of reconstruction of an on-shore pumping station combined with a water inlet of Chelyabinsk Metallurgical Plant (CMP) is developed. The authors give characteristics of the quality and amount of water, needed for the main production of CMP. The inspection of the on-shore pumping station combined with the water inlet of CMP is carried out. The need for reconstruction for reliability control and compliance with modern requirements of water intake of an industrial enterprise, which in turn is connected with the expansion of production at CMP is proven. The basic equipment is specified. It leads to the enlargement of the pumping station itself. 

Author Biographies

  • Irina Anatolevna Arkanova
    кандидат технических наук, профессор кафедры градостроительства, инженерных сетей и систем
  • Andrey Andreyevich Noskov
    монтажник санитарно-технических работ

Published

2017-07-31