IMPROVEMENT OF ORGANIZATIONAL AND TECHNOLOGICAL RELIABILITY OF CONSTRUCTION IN MODERN CONDITIONS
Abstract
The article presents data on the causes of violation of the terms of construction of objects,
based on the analysis of failures of private flows: organizational, technical, and technological ones.
The relevance of the study is explained by the need for timely commissioning of construction
projects due to the increase of organizational and technological reliability.
The article describes the method of temporary reservation, the method of accelerating the production
of works on the example of the calendar plan for construction of residential buildings,
which allows to solve such problems as: failure of the construction time of an object, lack of spread
of work, violation of the delivery schedules for material and technical resources, and irrational distribution
of funds.
The results of the use of the methods of temporary reservation and acceleration of work include:
improving the organizational and technological reliability of construction; and compliance
with the construction period by reducing the duration of individual flows, what compensates for early
downtime due to construction failures.